Road Project
Fairgrounds Rd Update 5-12-25
Fairgrounds Rd Project Update: 5-12-25 Milling and topsoil stripping began late last week. Grading on the first (southern) portion will continue this week. We completed the first 4,500 feet of grade staking last week. Please note: the gravel surface becomes...
Wild Plum Paving Update 5-6-25
Wild Plum Road Project Update: Tuesday, May 6th Paving on Wild Plum Rd. and Beach Ln (along with overlay on Whitetail Rd.) is slated to begin in the next week or two. Be advised of potential road delays/closures during this period and plan for alternate routes when...
Fairgrounds Road Construction Spring 2025
April 16, 2025 Dear Resident, Northern Township is undertaking the reconstruction of the entire length of Fairgrounds Road. The Township applied for, and was successful in receiving, a State LRIP (Local Road Improvement Program) grant that will fully fund the...